Top Risks

Ranking this week Risk Mitigation
1 wmi install will take too long try to get benchmark items w/o wmi develop alternate vbs not requiring wmi.
2 offline tools don't work as needed or expected  prioritize work on this. make sure we can collect feedback thoroughly from new users
3 online tools dont work as expected or as needed by eriders  get input asap re user needs, add content to easy user experience
4 unexpected differences in OS environments & language environments  get help from int'l testers.
5  insufficient testing time get volunteer help
6 upload synchronization not sufficient  could revisit after launch
7 online usage doesn't parallel offline usage leading to cognitive disconnect  try to role more improvements int TS online development, know what features we should try to ammend
8 hurdle for localization too high  identify needed resources to localize, maybe to support efforts of others
9 quirky installation of offline tools do best to make easy
10 Short development cycle be ready to drop last minor features on short notice 
still remain issues, but not actively being addressed now. Insufficient knowledge of and input from eRider community prior to commencement of development  

I'd like to invite eriders to view/review/test application as soon as we have a stable install.

getting as much as we can now. Building tools to allow flexibility later delivery and future changes to content.

Diversity of eRider community, especially across languages and cultures, is extreme. Involve diverse eriders. Build with future language translations in mind.
Highly diverse technical environments & operating system attributes & versions across regions. We'll need a diverse testing environment during dev as well as during beta periods to address this.

 

 

Ranking this week Ranking (7/14) Risk Mitigation
1 1    
2 2    
3 7    
4 3 Short development cycle scope features carefully, monitor priorities and progress closely
5 4 Developer is building offline tools for 1st time in this platform (VB) Address problem areas/potential bottlenecks early in development.
6 5 Developer lacks 1st hand familiarity with end users. Ric & Bill & eRiders are tapped fully. Phil will communicate re: development issues with developer eriders. 
7 6 Project management complicated by multiple stakeholders/ project owners. Setting clear project role lines, use project mgr to keep things on track.